Linear Accelerator Replacement

Client Robert Wood Johnson University Hospital in

× Back To Projects
× Back Home

Owner:
Robert Wood Johnson University Hospital
Faith Orsini
Administrative Director Construction Services
732.418.8406

Architect:
Stantec Architecture Inc.
Kristy Hollis
Associate
215.665.7000


Construction Budget:
$600,000

Area:
1,870 SF

Date of Completion:
2017

Replacement of (2) existing linear accelerators and renovation of existing procedure and control rooms. Scope included new electrical rough for new equipment and systems. The equipment was rigged to the floor through the elevator shaft. Work was completed in two phases within an occupied and operational radiation oncology suite.